Moser Baer Solar Limited (MBSL), has etched a new landmark by
commissioning a 32.2 MW solar farm in a record time of 39 days operating
at an optimum generation efficiencies from the day 1 of its operations.
The projects commissioned over 225 acres of land had multiple sub-
contractors working round the clock to ensure timely completion of the
project including getting it grid connected. The focus for the team
management was to avoid wastage, enormous coordination, speed and
managing the Installation like an Assembly line operation to ensure
timely completion of the Project with precision planning.
Speaking on the occasion, K.N. Subramaniam, CEO, Moser Baer Solar
Ltd. said, “The challenges were multifold like designing the solar farm
as per the best irradiation level of the area movement of modules to the
site in a short time, managing logistics, identifying right manpower
and training them, connecting to the grid among others. What made it
particularly challenging, the project was to be completed within 40
days! Our in-house designing experts and their understanding of the
solar business helped us to commission the solar farm in less than the
specified time. This experience sets a new benchmark in solar EPC and
should augur well for the Indian players.”
Shares of MOSER BAER INDIA LTD. was last trading in BSE at Rs.7.96 as
compared to the previous close of Rs. 7.59. The total number of shares
traded during the day was 622237 in over 1448 trades.
The stock hit an intraday high of Rs. 7.96 and intraday low of 7.22. The net turnover during the day was Rs. 4740787.
Source: Equity Bulls
No comments:
Post a Comment