India is expected to sign an
initial deal to export around 500 mega watts (MW) per day of power to
Pakistan this month when the trade ministers of the two south Asian
neighbours meet here.Sources said the initial wheeling of power would be around 500MW but could be increased.There are indications that Pakistan will increase the import to 2,000-2,500MW to meet the power shortage impacting its economy.
The wheeling of
power between the two nations is expected to energise trade ties,
resulting in Islamabad lowering the number of items on the negative list
— a step towards granting most favoured nation status (MFN) to India.
The grant of MFN
status means the two countries can trade on equal terms, giving each
other low tariffs and high import quotas. India granted Pakistan the MFN
status in 1996.India’s Central
Electricity Authority and Power Grid Corporation of India will be the
nodal technical agencies. Pakistan will have the National Transmission
and Despatch Company and Chief Engineering Advisor as its nodal
agencies.Officials said
there was a broad agreement that cross border trading would be done
through HVDC (high voltage direct current) coupling, as is being done
with Bangladesh, ensuring that both the grids operate independently.
As Lahore is near Punjab, it will be economical to transfer power through Amritsar, officials said.
The project will
require 45 kilometres of 220 kV transmission lines on both sides of
the border — 25 kilometres in India and 20 kilometres in the
neighbouring country. The tariff is likely to be around Rs 8 per unit, which is almost similar to the rates in Pakistan, sources said. Pakistan faces a
37 per cent, or 5,000MW, energy shortage and is desperately looking for
ways to bridge the huge shortfall. Power shortages, along with endemic
violence, have resulted in its textile mills moving to Bangladesh.At present,
Islamabad imports 35MW from Iran, which it plans to increase to 100MW.
It is also considering importing another 1,000MW from Tajikistan.
Power production
in Pakistan is only about 10,000-16,000MW against an installed capacity
of 20,800MW. The sector is plagued by old plants, poor maintenance and
high debt.
Source Telegraphindia
For any suggestion,request for any post please write us at admin@energymania.org
For any suggestion,request for any post please write us at admin@energymania.org
No comments:
Post a Comment